As full-service general contractor, Furrer+Frey was commissioned with the overall planning and installation of the overhead contact line system at the new V-Cableway transfer station Eigergletscher, including a switching sector with automatic earthing, chase lights system and contact wire reinforcement throughout the hall. We also installed special suspensions in the portal area and carried out extensive modifications to the existing Eigergletscher station. The direct entrance from the new facility into the Jungfrau Tunnel, as well as the gallery and tunnel expansion, also called for significant adjustments to the overhead contact line.